Construction Access at Water Treatment Plant
Community Hall Demolition to Begin This Week
Auction Item Viewing Opportunity
- All items will be sold as is, where is, with no warranties or guarantees expressed or implied.
- District staff are unable to provide information regarding the condition, history, operation, value, or suitability of specific items.
- Prospective bidders are responsible for conducting their own inspection and assessment of any items they may wish to purchase.
- The District assumes no liability for errors, omissions, or inaccuracies related to any information that may be available about auction items.
Boil Water Notice Lifted
Water Treatment Plant Upgrade
The current phase of work is progressing as planned and remains on schedule. A key piece of permanent treatment equipment, the new clarifier, will be delivered later this month or in early February.
Commissioning of the full permanent system is still expected in spring/summer 2026. Temporary disruptions to water service may be required at that time as part of final testing and tie-ins, and we will provide more information in advance of any planned service interruptions.
If you have any questions about the ongoing work, please contact Desirée LeBlanc, Director of Public Works & Engineering, at 250-783-1455 or by email at desiree@hudsonshope.ca.